A latent condition is a physical condition on or near a relevant site that could not have been reasonably anticipated by a contractor at the time of tendering. The contractor is required to have conducted all reasonable inspections of the site and obtained necessary reports including foundation data. The meaning of a latent condition and the options for relief will vary depending on the contract or project. It may depend on the amount of information available to the contractor before the entered into the contract. The smallest differences in written language and wording will result in substantially different outcomes. Read on to find out more about latent conditions.

What are examples of a latent condition?
Common examples of potential latent conditions include:
- Hazardous materials;
- Contaminated soil;
- Conditions below the ground such as rocks, cavities, underground structures or soil density;
- Hidden building services such as cabling, electricity, data or air conditioning ductwork that may be hidden above ceilings, below floors or behind walls; and
- Any other types of physical features, active or redundant, that could not be reasonably be anticipated.
Latent conditions exclude weather. It is important to note that a condition treated as latent in one contract, may not be latent for the purposes of another. In each case, the wording of a contact must be carefully considered to determine whether the condition is in fact a latent condition.
What is an example from a contract of a latent condition?
Examples of a latent condition that may be found in a contract include:
- 'In the event that a latent condition becomes apparent following commencement of the building, we may advise you of additional services that are required to remedy the latent condition.’
- ‘Once the order has been accepted, we reserve the right to cancel the order in the event that a latent condition becomes apparent.’
What are different types of latent condition clauses?
Although latent condition clauses may appear similar, latent condition definitions can vary between contracts. Differences to look out for include:
- Types of conditions (ground conditions or physical conditions);
- Location of the condition (on site or nearby);
- The quality of inspection the contractor is expected to have carried out; and
- The time of assessment to be made (i.e. the closing of tenders vs the date of the contract).
What are the elements of a latent clause?
A latent condition clause should answer these questions:
- What types of conditions are covered?
- What level of pre-contract due diligence is expected?
- What is the reference point for assessment?
- How and when must a claim be made? and
- What relief will be available?
What is the reference point for assessment?
To determine whether a particular condition is a latent condition, an assessment will be made regarding what the contractor should have anticipated at a certain point in time. This point of time will typically be at the time of the contractor’s tender, the date of the contract; or a date after the date of the contract with a specific regime.
How and when must a claim be made?
Assuming the contractor is permitted to claim relief, the clause will usually require certain notices to be given. Some contacts will be prescriptive and contain time limits, and a contractor may provide a statement identifying the latent condition encountered, the additional work required, resources required, time needed and necessary costs. This is so that if anything unexpected arises during the project, the principal can react to make fast decisions to mitigate the impact.
What relief will be available?
The latent condition clause should provide the relief that will be available to the contractor. The latent condition will usually be treated as a variation, so that the contractor can claim an extension of time, as well as an additional cost involved in overcoming the latent condition. The clause may sometimes limit the contractor’s right to direct third party costs, and they may exclude any entitlement to profit.
Relief for latent conditions will be a material consideration for both parties during the time of the tender.
How do you manage the risk of latent conditions?
Before entering a contract or site investigation, it is important for both parties (including principals and contractors) to agree as to where the risk of latent conditions lies. Consideration should be given to a range of matters including:
- If one party bear all the risk of latent conditions, or whether the risk and cost be shared;
- If a contractor will be responsible for risk, they must be allowed reasonable time to carry out a risk assessment and a site inspection to ensure that they identify potential additional risks and the associated costs;
- Whether any historical searches be available in relation to the subject site or neighbouring properties; and
- Parties must decide on a process for sharing knowledge of any potential latent conditions that may be present or which are discovered during site investigations.
What happens if liability for latent conditions are excluded?
If liability for latent conditions are excluded or limited by the contract, or you are prescribed to be liable, it is recommended that you seek legal advice prior to signing any documentation that may greatly limit the chances of turning profit on a project. Case law has determined that if a principal has a large amount of bargaining power, any exclusion clauses will be scrutinised and must be properly drafted.
Legal advice
If you are a principal and wish to create or exclude liability for any latent conditions, it is recommended that you seek legal advice before preparing any contract or tender documents. Legal Kitz business specialists can assist you so as to avoid complications when an unexpected hazard arises. Click here to book a FREE consultation with one of our highly experienced solicitors today or contact us at info@legalkitz.com.au or by calling 1300 988 954.
Disclaimer: This article is general information only and is not legal advice. It is current as at the date of publication shown above, does not take into account your circumstances, and reading it does not create a lawyer-client relationship. Laws change, so please obtain legal advice about your specific situation before acting or relying on this information.